본문으로 바로가기
  • 2013.12

    Construction of 1 berth (#8) with the capacity of DWT 50,000 ton at Godae pier

  • 2012.12

    Construction of 1 berth (#4) with the capacity of DWT 50,000 ton and 2 berths (#2, 3) with the capacity of DWT 30,000 ton each at Godae pier

  • 2012.12

    Construction of 1 berth (#8) with the capacity of DWT 20,000 ton and 2 berths (#12, 13) with the capacity of DWT 5,000 ton each at the Hyundai Steel steel product pier

  • 2012.07

    Construction of 7 berths with the capacity of DWT 3,000 ton each at the Sand pier

  • 2012.03

    Construction of 1 berth (#3) with the capacity of DWT 30,000 ton at the West pier cement pier

  • 2011.07

    Construction of 2 berths (#8, 9) with the capacity of DWT 50,000 ton each at the West pier grain pier

  • 2011.05

    Construction of 1 berth (#7) with the capacity of DWT 30,000 ton at Godae pier

  • 2010.12

    Construction of 1 berth (#2) with the capacity of DWT 50,000 ton at the East pier automobile pier

  • 2010.09

    Construction of 1 berth (#2) with the capacity of DWT 30,000 ton at the West pier cement pier

  • 2010.07

    Construction of 1 berth (#1) with the capacity of DWT 30,000 ton at the West pier cement pier

  • 2010.05

    Construction of 3 berths (#14, 15, 16) with the capacity of DWT 30,000 ton each at the East pier

  • 2010.02

    Container liners operated by MAERSK, the largest shipping company in the world, makes berth at Pyeongtaek, Dangjin Port

  • 2009.04

    Construction of 1 berth (#5) with the capacity of DWT 100,000 ton and 1 berth (#4) with the capacity of DWT 200,000 ton at the Hyundai Steel pier

  • 2009.03

    Designation of phase 1 port hinterland complex (free trade zone) for Pyeongtaek, Dangjin Port

  • 2008.12

    Construction of 2 berths (#2, 3) with the capacity of DWT 50,000 ton each at Godae pier

  • 2008.11

    Construction of 1 berth (#3) with the capacity of DWT 50,000 ton at the East pier

  • 2008.09

    Construction of 2 berths (#6, 7) with the capacity of DWT 50,000 ton each at the East pier

  • 2007.08

    Construction of 1 berth (#8) with the capacity of DWT 30,000 ton at the East pier

  • 2007.07

    Construction of 2 berths (#4, 5) at the East pier Kia Motors pier

  • 2007.06

    Construction of 2 berths (#4, 5) and 1 berth (#7) with the capacity of DWT 30,000 ton each at the Hyundai Steel steel products pier

  • 2005.02

    Construction of the international passenger pier

  • 2004.12

    Port name changed to Pyeongtaek, Dangjin Port

  • 2004.11

    Construction of 1 berth (#9) with the capacity of DWT 30,000 ton at the East pier

  • 2003.07

    Establishment of the Pyeongtaek Regional Maritime Affairs and Port Office

  • 2001.08

    Construction of the international passenger terminal

  • 2001.08

    Construction of 2 berths (#6, 7) with the capacity of DWT 30,000 ton each at the West pier

  • 2000.10

    First container liner enters port (Pyeongtaek-Hong Kong)

  • 1997.12

    Construction of 4 berths (#10, 11, 12, 13) with the capacity of DWT 30,000 ton each at the East pier

  • 1997.11

    Construction of 1 berth (#1) with the capacity of DWT 5,000 ton at Godae pier

  • 1996.07

    Selected as one of 3 national project ports and 5 national development projects

  • 1986.12

    Opened as a type 1 designated port 「international trade port」

  • 1986.10

    First LNG liner enters port